12:00 am August 29, 2005: Louisiana Emergency Officials Discuss Response Plan
Around midnight, local emergency officials from southeastern Louisiana hold a teleconference with FEMA to discuss plans for responding to Katrina’s aftermath. Local officials are so certain of catastrophe that they ask FEMA to include extra medical staff in its first wave of responders to help the expected casualties. At this point, officials are reportedly following a plan drafted only months ago, as a result of the Hurricane Pam exercise conducted in 2004 (see July 19-23, 2004). [Chicago Tribune, 9/11/2005]
Note - Following the 2004 Hurricane Pam exercise, Innovative Emergency Management (IEM issued a Draft Southeast Louisiana Catastrophic Hurricane Functional Plan (Draft Plan) on August 6, 2004. [Federal Emergency Management Agency, 8/6/2004
] Whether local officials are following this draft plan, or a later plan, remains unclear at this time. The Chicago Tribune reports that the plan in place provides that local officials should be prepared to deal with the aftermath of the storm for 48 to 60 hours (or until August 31). However, the Draft Plan expressly contemplates that local search and rescue resources will be unavailable to rescue the estimated 500,000 people in flooded or damaged areas. [Federal Emergency Management Agency, 8/6/2004, pp. 69-70, 72
] Thus, the Louisiana Department of Wildlife and Fisheries, and the US Coast Guard are expected to serve as the primary first-responders, while local officials are tasked with requesting assistance. [Federal Emergency Management Agency, 8/6/2004, pp. 70-74
] Further, while local parishes are tasked with identifying required support, the Plan recognizes that they may be unable to do so: “State and Federal SAR operations personnel will respond to Parishes without a request if initial assessment indicates that the Parish is severely damaged and is not capable of requesting assistance.”
[Federal Emergency Management Agency, 8/6/2004, pp. 75
] The Plan also contemplates that 500,000 residents will need transport from the initial search and rescue staging area to shelters, and that because the Louisiana National Guard will be otherwise tasked, it will be unable to meet this transportation need. [Federal Emergency Management Agency, 8/6/2004, pp. 27-28
]